As part of new moves to up power supply, the Federal Government has unveiled plans to begin work on electricity transmission lines in over six states to boost power supply in the country.
The possibility of the new plan cannot be unconnected to the recent clearing of about 77 containers laden with electricity construction materials formally stranded at the Apapa Port in the last eight years.
Explaining issues at the commencement of the delivery of Transmission Company of Nigeria (TCN) stranded containers, the Minister of Power, Works and Housing, Babatunde Raji Fashola, listed proposed works to include construction of new Abeukuta-Igboora double transmission line and 132KV double-circuit Tee-off at Igboora-Igangan.
Others are the construction of 2×60 Mega Volt Amp1 (MVA) 32/33kv-substation at Odogunyan and construction of 2x60MVA, 132/33Vsubsation at Ayobo, Ikeja West Ayobo 132KV Direct Current (DC ) transmission lines and 2x132kvline bays extension at Ikeja West.
Fashola, who was represented by the Managing Director/Chief Executive Officer of TCN, Dr. Abubaka Atiku, said that the release of the containers would also help in the construction of Benin North-Osogbo 330kv DC line with turning in and out to new Akure substation.
The Minister made it clear that “The power equipment will assist in the construction of Kaduna-Jos 330KV DC line. Plateau and Kaduna states; installation of 1x60MVA and 1×30 MVA 132/33KV power transformers, auxiliary equipment and devices at GCM transmission substation in Onisha; construction of 330KV D/C Kaduna power plant – Mando substation transmission line; and others,” he said.
Business Hilights gathered that it took several negotiations for the release of these power materials due to the accrued demurrage.
Besides, a lot of hard work was been put into negotiations for the release of these power materials due to the accrued demurrage as a result of the suspension of the issuance of import duty exemption certificate for some period in 2014.
In his welcome address, Managing Director, of Duncan Bonded Terminal, Dr. Godfrey Bawa said that as a major and front-runner Terminal Operator in Lagos, the company provides off-dock facilities to the Ports Authority for the purpose of eliminating congestion in the port.