Lack of power transmission lines to national grid frustrating Kashimbilla Dam in Taraba

Chevron
Advertisements
Ad 2
Advertisements
Ad 3
Advertisements

The Federal government, through Ministry of Water Resources has disclosed that the delay in the connection of power transmission lines to the national grid was responsible for non-completion of the Kashimbilla Multipurpose Dam in Taraba.

In an interview, the Acting Director, Dams and Reservoir Operations, in the ministry, Mr. Lawal Muhammad, said the dam and the power generating components of the project had been completed.

According to him, the outstanding aspect of the project was the erection of power transmission lines that would convey electricity to the national grid, and he noted that the responsibility belongs to the Federal Ministry of Power, Works and Housing.

While maintaining that work on water supply component of the dam had gone far, while work on the reticulation network had reached an advanced stage, Muhammad said that the irrigation component of the dam had been designed, while work on it had also reached an advanced stage.

The acting Director revealed further that “We are studying the design; after the approval of the design for the contractor, we can then give him the go-ahead to start the construction,” disclosing that the dam had been completed, while its water had been impounded.

The ministry official also hinted that the dam project was also executed to control water surge whenever water was released from Lake Nyos in Cameroon, stressing that the water, which was recently released from the lake, was intercepted by the dam in order to prevent flooding in the downstream parts of River Benue.

“So now, instead of allowing the body of water to stay idle there, we can now utilise it to provide potable water for the people in Takum village and other areas of Taraba State,’’ he said.

He added that when the dam was completed, it would have the capacity of generating 40 megawatts of hydro-power, and assured that the power generation would be a plus to electricity supply to the citizens.

Business Hilights recalls that the Federal Executive Council (FEC) recently approved an additional N46.15 billion for the completion of the remaining 10 per cent of the Kashimbila Dam project.

Explaining the reason behind the approval, the Minister of Water Resources, Mr Suleiman Adamu, described the project as one of the ministry’s flagship projects, adding that it would be completed and put to use in 12 months.

He said “The dam was identified by the United Nations (UN) as one of the key projects that we need to do to provide a buffer against flooding along the River Benue, which of course you remember in 2012 was quite devastating”.

“Certainly, flood around the River Benue has always been a recurring decimal, in view of the dams which have been constructed by Cameroon. Whenever water is released unsystematically, it continues to cause a lot of damage,” the Minister averred.